The application period for fiscal year (FY) 2024-25 is now closed.
Eligibility | Funding | Timeline and Cycle Details
The Department of Resources Recycling and Recovery (CalRecycle) administers a program to provide opportunities for the local governments/other eligible jurisdictions to receive payments for used oil and used oil filter collection/recycling programs.
Eligibility
Applicants
- Eligible applicants are limited to local governments, which are defined in statute as “any chartered or general law city, chartered or general law county, or any city and county.” CalRecycle may make a payment to another entity that will implement the program on behalf of a local government (in lieu of making a payment to that local government) with the agreement of that local government.
Activities
To be eligible to apply for a payment under this program, applicants must:
- Have either one certified used oil collection center per 100,000 residents and/or a curbside collection program that includes used oil/used oil filter collection at least monthly.
- Have a public education component (in their program) that informs the public of locally available used oil/used oil filter collection/recycling opportunities.
- Accept the terms set out in the OPP Cycle 15 Guidelines and be in compliance with the program provisions described in PRC section 48690 et seq., notably PRC sections 48674, 48690, and 48691.
Funding
- $6,000,000 is available (the amount available is subject to change, based on the availability of oil funds) for fiscal year (FY) 2024-25.
- Per Capita Funding
- Payments are calculated per capita using the Department of Finance’s population statistics.
- Small jurisdictions will be provided a minimum award of $5,000 for cities and $10,000 for counties.
- Jurisdictions may also apply regionally and pool their funds.
Timeline and Cycle Details
Dates | Activity and Details |
---|---|
June 26, 2024 | Application Due Date
|
July 24, 2024 | Secondary Due Date – Required Authorization documents
|
Spring 2025 | Payments Awarded A single payment will be made in Spring 2025, unless an early payment (approximately January 2025) is requested by the applicant and subsequently approved by CalRecycle. Payment dates may be subject to change. Funding is subject to State budget approval |
July 1, 2024- June 30, 2026 | Performance Period The term is 24 months. Funding will be available for expenditure for the new cycle on July 1, 2024, and be available for expenditure through June 30, 2026. Refer to the OPP Cycle 15 Guidelines for further information and any exceptions. |
August 15, 2025 and August 15, 2026 | Annual Report Due Dates Submission of online Annual Report is required and is due no later than August 15 of each year during performance period. If the due date falls on a Saturday or Sunday, the online report must be submitted by the following Monday. |